This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 3,850 linear feet of 10 to 18-inch gravity sewer, 17 associated manholes, and 37 service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-0144C |
Council District(s): | 3 |
Sewer basin: | Whites Creek |
Designer: | Barge Waggoner Sumner & Cannon, Inc. |
Contractor: | Layne Inliner, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | July 2013 | March 2015 |
Permitting/Bid/Award | March 2015 | June 2015 |
Construction | June 2015 | December 2015 |