West Park Equalization Facility Phase II
Completed December 2018
The project is a partnership between Metro Parks and Metro Water Services to accomplish two significant goals for the community:
- Improve and expand the recreational opportunities within West Park
- Provide an additional storage tank for the benefit of improving Richland Creek's water quality by addressing existing overflows
The West Park project will include the construction of a 260 foot diameter, 37 foot high circular wet weather storage tank similar to the one existing on site. The storage tank will be utilized when sewer flows exceed the capacity of the West Park Pump Station. The peak flows are stored until the flows in the system recede, and the stored volume can be conveyed through the pump station to treatment. Without the construction of this facility, flows in excess of the pump station capacity resulted in sanitary sewer overflows.
Park improvements include a new 300 foot adult softball field, basketball court, large restroom/picnic pavilion, walking trail, and 6,000 square foot youth playground with a rubberized safety surface. The softball field will be completely renovated with fencing, an irrigated outfield, and new sports lighting. A 12 foot wide perimeter greenway trail will follow along Richland Creek and create a loop within the park for walking, running, and bicycling. Outdated restrooms will be replaced with a new building complete with a covered picnic area. Open space and landscaping will be enhanced throughout the park to improve its overall aesthetic appearance.
Project Details
Project Type: | Equalization Facility |
Project Area Map: | View map |
Metro Project #: | 11-SC-0101 |
Council District(s): | 20 |
Sewer basin: | Whites Creek |
Designer: | Hazen and Sawyer, P.C. for tank design and Lose and Associates for landscape architectural services |
Contractor: | Cleary Construction, Inc. |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | May 2012 | December 2014 |
Permitting/Bid/Award | December 2014 | April 2015 |
Construction | April 2015 | December 2018 |