Vandiver Rehabilitation
Completed January 2020
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 55,300 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-109A |
Council District(s): | 9 |
Sewer basin: | Dry Creek |
Designer: | Water Management Services, LLC |
Contractor: | Insituform Technologies, Inc. |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | December 2016 | August 2017 |
Permitting/Bid/Award | August 2017 | March 2018 |
Construction | March 2018 | January 2020 |