Vandiver Pump Station Upgrades

To convey additional flows and remediate nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity and the upgrade of one of the two associated force mains.

Project Details

Project Type: Pump Station
Project Area Map: View map
Metro Project #: 11SC0109
Council District(s): 9
Sewer basin: Dry Creek
Designer: Brown & Caldwell
Contractor: TBD

Project Timeline

Phase Start Finish
Design June 2024 February 2026
Permitting/Bid/Award February 2026 July 2026
Construction July 2026 July 2028