Tuckahoe & Nesbitt Rehabilitation

This project was developed to renew aging infrastructure and to address overflows by reducing the amount of rainfall that can enter the system through defects. It is primarily focused on the rehabilitation of over 400 manholes throughout the project area. The project also includes rehabilitation of approximately 3,500 linear feet of existing sewer lines by cured-in-place-pipe lining, service replacements by excavation, trenchless service renewals, and other miscellaneous sewer-related work.

The rehabilitation work will primarily occur in easements and public roadways. Construction methods will include trenchless technologies (pipe and manhole lining) to minimize excavation in streets and properties. However, some excavation will be necessary on certain streets, in existing easements, and in public rights-of-way for sewer service renewals to individual properties. Temporary piping for diversion pumping may be installed on the ground. Roadways and properties disturbed by the work will be restored to their original conditions as closely as possible in a manner that will ensure that MWS can maintain future access to the public sewer infrastructure.

The project is expected to last 9 months, although due to the nature of the work, many locations will not experience any impacts for several months at a time.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 11SC144B
Council District(s): 3
Sewer basin: Whites Creek
Designer: CWN
Contractor: TBD

Project Timeline

Phase Start Finish
Design October 2023 April 2024
Permitting/Bid/Award April 2024 September 2024
Construction September 2024 June 2025