Smith Springs Rehabilitation - Future Areas
This multiphase project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. This project consists of the evaluation and rehabilitation (as necessary) of up to 300,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | TBD |
Council District(s): | 8, 29 |
Sewer basin: | Central |
Designer: | TBD |
Contractor: | TBD |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | January 2027 | January 2028 |
Permitting/Bid/Award | July 2027 | May 2028 |
Construction | November 2027 | February 2030 |
Project Photos
No photos available.