Completed October 2018
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 58,800 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-120B |
Council District(s): | 29, 33 |
Sewer basin: | Central |
Designer: | Civil Infrastructure Associates, LLC |
Contractor: | SBW Constructors, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | February 2016 | August 2016 |
Permitting/Bid/Award | August 2016 | January 2017 |
Construction | January 2017 | October 2018 |