Smith Springs Rehabilitation - Area 1 - Priest Lake Meadows
Completed March 2017
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 64,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-0120A |
Council District(s): | 29 |
Sewer basin: | Central |
Designer: | ICA Engineering |
Contractor: | Layne Inliner, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | February 2015 | October 2015 |
Permitting/Bid/Award | October 2015 | February 2016 |
Construction | February 2016 | March 2017 |