Shelby Park Rehabilitation - Area 5 - Cooper Ln
Completed January 2019
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 52,200 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-105E |
Council District(s): | 6, 7 |
Sewer basin: | Central |
Designer: | Fulghum, MacIndoe & Associates, Inc. |
Contractor: | Insituform Technologies, Inc. |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | June 2016 | March 2017 |
Permitting/Bid/Award | March 2017 | August 2017 |
Construction | August 2017 | January 2019 |