Neely's Bend Rehabilitation
Completed February 2015
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consisted of the evaluation of approximately 31,400 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements. The resulting construction project includes the rehabilitation of approximately 22,000 linear feet of 8 to 18-inch gravity sewer, 110 associated manholes, and 250 service connections.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-0106 |
Council District(s): | 9 |
Sewer basin: | Dry Creek |
Designer: | Cardozo Engineering, Inc. |
Contractor: | Insituform Technologies, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | September 2012 | June 2013 |
Permitting/Bid/Award | June 2013 | December 2013 |
Construction | December 2013 | February 2015 |