Mill Creek Rehabilitation - Franklin Limestone Road

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 49,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 11SC118D
Council District(s): 28,32
Sewer basin: Central
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design January 2029 July 2029
Permitting/Bid/Award July 2029 December 2029
Construction October 2029 August 2031