Loves Branch Pump Station Upgrades

To convey additional flows and remediate nearby sanitary sewer overflows, this project includes the construction of a new pump station with greater capacity and the upgrade of a portion of the associated force main.

Project Details

Project Type: Pump Station
Project Area Map: View map
Metro Project #: 11SC0108
Council District(s): 7
Sewer basin: Dry Creek
Designer: Brown & Caldwell
Contractor: TBD

Project Timeline

Phase Start Finish
Design January 2027 March 2028
Permitting/Bid/Award March 2028 August 2028
Construction August 2028 November 2030