In order to provide increased conveyance capacity and address existing restrictions within the sewer system, approximately 550 linear feet of gravity sewer pipe will be replaced with larger sewers.
Project Details
Project Type: | Conveyance |
Project Area Map: | View Map |
Metro Project #: | 22SC0032 |
Council District(s): | 21 |
Sewer basin: | Central |
Designer: | CWN |
Contractor: | SBW Constructors LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | April 2022 | July 2022 |
Permitting/Bid/Award | August 2022 | October 2022 |
Construction | October 2022 | April 2023 |