Hurricane Creek Pipe Improvements
In order to provide increased conveyance capacity and address existing restrictions within the sewer system, approximately 12,100 linear feet of gravity sewer pipe will be replaced with larger sewers.
Project Details
Project Type: | Conveyance |
Project Area Map: | View Map |
Metro Project #: | 11SC0116 |
Council District(s): | 8,32 |
Sewer basin: | Central |
Designer: | HDR Engineering |
Contractor: | Garney Companies, Inc. |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | July 2016 | November 2017 |
Permitting/Bid/Award | August 2021 | June 2022 |
Construction | June 2022 | February 2025 |
Project Photos
View fullsize
Chemical Tank Removal
View fullsize
Installing Rebar and Waterstop in Structure Slab
View fullsize
Grading 30" Diameter Pipe
View fullsize
Sealing Influent Structure
View fullsize
Concrete Cap Pour
View fullsize
Installing 5' Diameter Manhole
View fullsize
Beginning 42" Road Bore
View fullsize
42 in Road Bore & Jack
View fullsize
30" Fiberglass Reinforced Pipe / Graduated Spacers
View fullsize
Placing Shot Rock in Pipeline Trench
View fullsize
Grading 36" Railroad Bore
View fullsize
Installing 30" Auger w/ Casing Pipe
View fullsize
Checking Grade on 30" Ductile Iron Pipe
View fullsize
Installing Manhole
View fullsize
Trenching Rock
View fullsize
24" Bore and Jack under CSX Railroad
View fullsize
6" Service Line Install
View fullsize
Installing 8" D.I.P. with Spacers
View fullsize
Manhole Invert Work
View fullsize
Abandoning Manhole
View fullsize
Beginning 24" Bore and Jack