Howse Avenue Force Main Replacement
Replacement of approximately 3200 feet of existing 16-inch force main and installation of a portion (500 feet) of new force main which is part of the Neely's Bend Pump Station Upgrades project.
Project Details
Project Type: | Conveyance |
Project Area Map: | View map |
Metro Project #: | 21SC0002 |
Council District(s): | 7, 9 |
Sewer basin: | Central |
Designer: | Civil Infrastruture Associates |
Contractor: | Cleary Construction, Inc. |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | July 2021 | March 2022 |
Permitting/Bid/Award | March 2022 | February 2023 |