Henry Ford Drive Rehabilitation

This project was developed to renew aging sewer infrastructure and to address overflows by reducing the amount of rainfall that can enter the system through defects. It consisted of the evaluation of approximately 58,500 linear feet of gravity sewer to determine necessary repairs. The resulting work consists of the rehabilitation of approximately 49,000 linear feet of existing sewer lines by cured-in-place-pipe lining, service replacements by excavation, trenchless service renewals, manhole rehabilitation, and other miscellaneous sewer-related work.

The rehabilitation work will primarily occur in easements and public roadways. Construction methods will include trenchless technologies (pipe and manhole lining) to minimize excavation in streets and properties. However, some excavation will be necessary on certain streets, in existing easements, and in public rights-of-way for sewer service renewals to individual properties. Temporary piping for diversion pumping may be installed on the ground. Roadways and properties disturbed by the work will be restored to their original conditions as closely as possible in a manner that will ensure that MWS can maintain future access to the public sewer infrastructure.

The project is expected to last sixteen months, although due to the nature of the work, many locations will not experience any impacts for several months at a time.

Project Details

Project Type: Conveyance
Project Area Map: View Map
Metro Project #: 11SC0146
Council District(s): 20
Sewer basin: Whites Creek
Designer: CIA
Contractor: Insituform Technologies, LLC

Project Timeline

Phase Start Finish
Design January 2023 June 2023
Permitting/Bid/Award January 2024 May 2024
Construction May 2024 September 2025

Project Photos