Gibson Creek Equalization Facility
This project consists of the construction of a 10 million gallon pre-stressed concrete tank and a 22 million gallons per day pump station. The storage tank is utilized when sewer flows exceed the capacity of the existing sewer system. The peak flows are stored until the flows in the system recede, and the stored volume can be conveyed through the system to treatment. Without the construction of this facility, flows in excess of the system capacity resulted in sanitary sewer overflows.
Project Details
Project Type: | Equalization Facility |
Project Area Map: | View map |
Metro Project #: | 11SC0139 |
Council District(s): | 7 |
Sewer basin: | Dry Creek |
Designer: | Smith Seckman Reid, Inc. |
Contractor: | Reeves Young, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | September 2016 | December 2017 |
Permitting/Bid/Award | December 2020 | August 2021 |
Construction | August 2021 | February 2024 |
Project Photos
View fullsize
Safety Station & DOL Awning Built
View fullsize
Placing Blasting Mats
View fullsize
Welding H-Piles
View fullsize
Drilling
View fullsize
Cutting I-Beam for Pinning
View fullsize
Rock Hammering Pump Station
View fullsize
Drill Tech Testing Rock Anchors with CWN
View fullsize
Drill Tech Grouting Rock Anchors
View fullsize
Placing Mud Mat in EQ Tank Area and Vibrating Concrete
View fullsize
PreCon Tank Installation
View fullsize
Pour For Rebar Inspection
View fullsize
Pipe Installation at Pump Station
View fullsize
Elevation Verfication
View fullsize
Shotcrete for EQ Tank
View fullsize
Interior Circumfrence Steel Installation
View fullsize
Hanging Outside Face Vertical Rebar
View fullsize
Pre-stressing EQ Tank
View fullsize
Removing the Shoring Inside Tank
View fullsize
Masonry Work
View fullsize
Metal Roof Install
View fullsize
6 inch Water Fire Lines
View fullsize
Burying Electrical Lines
View fullsize
New Pump Station
View fullsize
EQ Tank
View fullsize
New Pump Station
View fullsize
Site Restoration