Foster Avenue Rehabilitation

This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 53,600 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 11SC0115
Council District(s): 16
Sewer basin: Central
Designer: Civil Infrastructure Associates, LLC
Contractor: Insituform

Project Timeline

Phase Start Finish
Design May 2022 November 2022
Permitting/Bid/Award December 2022 April 2023
Construction April 2023 December 2024