Ewing Creek - Brick Church Equalization Facility
Completed June 2019
This project consists of the construction of a 10.6 million gallon pre-stressed concrete tank and an 18 millon gallons per day pump station. The storage tank is utilized when sewer flows exceed the capacity of the existing sewer system. The peak flows are stored until the flows in the system recede, and the stored volume can be conveyed through the system to treatment. Without the construction of this facility, flows in excess of the system capacity resulted in sanitary sewer overflows.
Project Details
Project Type: | Equalization Facility |
Project Area Map: | View map |
Metro Project #: | 11-SC-0110 |
Council District(s): | 3 |
Sewer basin: | Whites Creek |
Designer: | GRW Engineers, Inc. |
Contractor: | Cumberland Valley Constructors, Inc. |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | August 2015 | December 2016 |
Permitting/Bid/Award | December 2016 | May 2017 |
Construction | May 2017 | June 2019 |
Project Photos
View fullsize
Project Map
View fullsize
Pre-Blast Drilling
View fullsize
Hauling Excavated Material Offsite
View fullsize
Excavating and Running Rock Crushers
View fullsize
Excavation For Tank
View fullsize
Concrete Pour
View fullsize
Tank Floor
View fullsize
Scaffolding Construction
View fullsize
Tank Floor Concrete Pour
View fullsize
EQ Tank Walls Ready for Shotcrete
View fullsize
Suspended Beams and Roof Slab
View fullsize
Shotcrete Application
View fullsize
Shotcrete Application
View fullsize
Equalization Tank
View fullsize
Painted EQ Tank
View fullsize
16 / 22 Inside Wet Well
View fullsize
Project Site
View fullsize
Bio-Retention Pond
View fullsize
Concrete Framework for Curb
View fullsize
EQ Tank/Site Overview
View fullsize
Fencing Around EQ Tank
View fullsize
Paving