Driftwood Equalization Facility
Completed November 2013
This project increased the storage capacity of the existing Driftwood facility by 3.2 million gallons and corrected operational electrical defects at the site. Through these improvements, the storage facility is now able to capture the additional flow generated from most rainfall events, preventing the release of combined sewage to the Cumberland River.
Project Details
Project Type: | Equalization Facility |
Project Area Map: | View map |
Metro Project #: | 11-SC-0067 |
Council District(s): | 19 |
Sewer basin: | Central |
Designer: | Smith Seckman Reid, Inc. |
Contractor: | Haren Construction Co. Inc |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | August 2011 | April 2012 |
Permitting/Bid/Award | April 2012 | July 2012 |
Construction | July 2012 | November 2013 |