Dodson Chapel and McCrory Creek Study and Future Projects
This project consists of extensive flow monitoring in the winter/spring of 2022, followed by an update to the hydraulic model and an evaluation of alternatives to address the overflows. The assessment and proposed corrective actions will be summarized in a supplemental report submitted in mid 2023
Project Details
Project Type: | Rehabilitation |
Project Area Map: | |
Metro Project #: | |
Council District(s): | 11,12,13,14,15 |
Sewer basin: | Central |
Designer: | TBD |
Contractor: | TBD |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | December 2026 | June 2029 |
Permitting/Bid/Award | June 2027 | June 2029 |
Construction | December 2027 | April 2031 |