Cowan Riverside Rehabilitation - Area 1 - Jones Avenue
Completed June 2015
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consisted of the evaluation of approximately 50,200 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements. The resulting construction project includes the rehabilitation of approximately 40,000 linear feet of 8 to 15-inch gravity sewer, 230 manholes and 630 service connections.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11-SC-0103A |
Council District(s): | 5, 8 |
Sewer basin: | Central |
Designer: | Parsons Brinckerhoff, Inc. |
Contractor: | Insituform Technologies, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | February 2013 | September 2013 |
Permitting/Bid/Award | September 2013 | January 2014 |
Construction | January 2014 | June 2015 |