Cleeces Ferry Rehabilitation - Area 2 - Hillwood Boulevard

This project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 26,000 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 11SC145B
Council District(s): 20, 23
Sewer basin: Whites Creek
Designer: TBD
Contractor: TBD

Project Timeline

Phase Start Finish
Design October 2024 April 2025
Permitting/Bid/Award April 2025 August2025
Construction August 2025 November 2026