Berwick Trail Pipe Improvements
Approximately 2,600 linear feet of gravity conveyance upgrades, increasing in diameter from 8 inches to a range of 12 inches to 18 inches.
Project Details
Project Type: | Conveyance |
Project Area Map: | View map |
Metro Project #: | 11SC0136 |
Council District(s): | 9 |
Sewer basin: | Dry Creek |
Designer: | TBD |
Contractor: | TBD |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | February 2026 | August 2026 |
Permitting/Bid/Award | February 2027 | August 2027 |
Construction | August 2027 | December 2028 |