Annual Rehabilitation - Haynes Estates

This project was identified to reduce wet-weather flows within the sewer system by addressing observed sources of infiltration and inflow through sewer rehabilitation. It also considers nearby sewers for inclusion in the project based on their condition, the likelihood of water migration to adjacent sewers, and the impact to customers. Work consists of the rehabilitation of approximately 25,000 linear feet of existing sewer lines by cured-in-place-pipe lining, service replacements by excavation, trenchless service renewals, manhole rehabilitation, and other miscellaneous sewer-related work.

Most of the rehabilitation work will occur in easements and public roadways. Construction methods will include trenchless technologies (pipe and manhole lining) to minimize excavation in streets and properties. However, some excavation will be necessary on certain streets, in existing easements, and in public rights-of-way for sewer service renewals to individual properties. Temporary piping for diversion pumping may be installed on the ground. Roadways and properties disturbed by the work will be restored to their original conditions as closely as possible in a manner that will ensure that MWS can maintain future access to the public sewer infrastructure.

Project Details

Project Type: Rehabilitation
Project Area Map: View Map
Metro Project #: 24SC0245
Council District(s): 1, 2
Sewer basin: Annual Rehabilitation
Designer: CWN
Contractor: Insituform Technologies, LLC

Project Timeline

Phase Start Finish
Design June 2024 November 2024
Permitting/Bid/Award October 2024 March 2025
Construction March 2025 March 2026

Project Photos