Annual Rehabilitation - Bordeaux and Metro Center
This project was identified to reduce wet-weather flows within the sewer system by addressing observed sources of infiltration and inflow through sewer rehabilitation. It also considers nearby sewers for inclusion in the project based on their condition, the likelihood of water migration to adjacent sewers, and the impact to customers. Work consists of the rehabilitation of approximately 21,000 linear feet of existing sewer lines by cured-in-place-pipe lining, service replacements by excavation, trenchless service renewals, manhole rehabilitation, and other miscellaneous sewer-related work.
Most of the rehabilitation work will occur in easements, public roadways, and commercial parking areas. Construction methods will include trenchless technologies (pipe and manhole lining) to minimize excavation in streets and properties. However, some excavation will be necessary on certain streets, in existing easements, and in public rights-of-way for sewer service renewals to individual properties. Temporary piping for diversion pumping may be installed on the ground. Roadways and properties disturbed by the work will be restored to their original conditions as closely as possible in a manner that will ensure that MWS can maintain future access to the public sewer infrastructure.
The project is expected to last 16 months, although due to the nature of the work, many locations will not experience any impacts for several months at a time.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 22SC0241 |
Council District(s): | Numerous |
Sewer basin: | Annual Rehabilitation |
Designer: | CWN |
Contractor: | Inliner Solutions, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | August 2022 | Jly 2023 |
Permitting/Bid/Award | July 2023 | December 2023 |
Construction | December 2023 | December 2024 |