Annual Rehabilitation FY2017 - Shepherd Hills
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as needed) of approximately 59,900 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 17SC017B |
Council District(s): | 10 |
Sewer basin: | All |
Designer: | Dempsey, Dilling & Associates, P.C. |
Contractor: | Insituform Technologies LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | August 2017 | October 2017 |
Permitting/Bid/Award | July 2021 | October 2021 |
Construction | October 2021 | December 2022 |