Annual Rehabilitation FY2017 Dry Creek
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as needed) of approximately 57,900 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 17SC017A |
Council District(s): | 3, 8, 9, Multiple |
Sewer basin: | Dry Creek |
Designer: | Fulghum, MacIndoe & Associates, Inc. |
Contractor: | SWB Contractors, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | March 2017 | September 2017 |
Permitting/Bid/Award | August 2020 | September 2021 |
Construction | September 2021 | April 2023 |