Annual Rehabilitation FY2016 - South Hurricane Creek
Completed February 2018
Evaluation and rehabilitation of approximately 53,400 linear feet of sewer, manholes, and laterals within Metro’s rights-of-way and easements with the goals of reducing rainfall-derived infiltration and inflow (RDII) and renewing existing infrastructure for the southern Hurricane Creek sewer basin.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 16-SC-0009 |
Council District(s): | 33 |
Sewer basin: | All |
Designer: | Hethcoat & Davis, Inc |
Contractor: | Insituform Technologies, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | March 2016 | December 2016 |
Permitting/Bid/Award | December 2016 | May 2017 |
Construction | May 2017 | March 2019 |