Annual Rehabilitation FY2014 - Whites Creek Trunk
Completed March 2018
This project was developed to renew aging infrastructure and to address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as needed) of approximately 55,800 linear feet of gravity sewer, associated manholes, and service laterals within Metro's right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 14-SC-0041 |
Council District(s): | 1, 2, 3 |
Sewer basin: | All |
Designer: | Hethcoat & Davis, Inc |
Contractor: | SAK Construction, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | October 2014 | August 2015 |
Permitting/Bid/Award | August 2015 | January 2016 |
Construction | January 2016 | March 2019 |
Project Photos
View fullsize

Project Map
View fullsize
CCTV
View fullsize
CIPP Lining
View fullsize

CIPP
View fullsize

Bypass Pumping
View fullsize
Inserting Lay Flat Liner
View fullsize

Cleanout Installed
View fullsize

Large Diameter CIPP Installation
View fullsize

Large Diameter CIPP (42-Inch)
View fullsize

54 In Liner for Over-the-Hole Shot
View fullsize
Gabion Baskets Filled
View fullsize

Gabion Baskets
View fullsize

Placed Rip Rap
View fullsize

Stream Bank Restoration
View fullsize

CIPP Conveyor
View fullsize

Bypass Pumping
View fullsize

Large Diameter CIPP Equipment Setup
View fullsize

Large Diameter CIPP