28th Avenue Rehabilitation – Future Areas
This multiphase project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of up to 193,000 linear feet total of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | TBD |
Council District(s): | 20, 21 |
Sewer basin: | Central |
Designer: | TBD |
Contractor: | TBD |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | April 2027 | December 2029 |
Permitting/Bid/Award | October 2027 | March 2030 |
Construction | February 2028 | July 2031 |