28th Avenue Rehabilitation – Area 2 – Batavia Street
This project was developed to renew aging infrastructure and address downstream overflows by reducing the amount of rainfall that can enter the system through defects. It consists of the evaluation and rehabilitation (as necessary) of approximately 49,600 linear feet of gravity sewer, associated manholes, and service laterals within Metro’s right-of-way and easements.
Project Details
Project Type: | Rehabilitation |
Project Area Map: | View map |
Metro Project #: | 11SC135B |
Council District(s): | 21 |
Sewer basin: | Central |
Designer: | Fulghum, MacIndoe & Associates, Inc. |
Contractor: | SAK Construction, LLC |
Project Timeline
Phase | Start | Finish |
---|---|---|
Design | May 2020 | February 2021 |
Permitting/Bid/Award | March 2022 | July 2022 |
Construction | July 2022 | July 2024 |